Incident
South Africa Telkom Network Outage
Affected services:
Telkom Mobile South Africa Network
Connectivity across the Telkom network has been fully restored. The issue is now resolved, and all services are operating normally.
May 25, 4:05 PM
Connectivity is being restored across the Telkom network. We will continue to monitor the situation and will provide confirmation once services are fully stable.
May 25, 3:46 PM
We have received reports of connectivity issues affecting users on the Telkom network in South Africa. Our team is actively investigating the matter with Telkom. At this time, all iONLINE systems remain fully operational.
May 25, 3:44 PM
Maintenance
Vodacom Emergency Maintenance - 12th May 23h00
12 May 21:00 - 12 May 21:37 2026 UTC
Estimated duration: 37 minutes 43 seconds
Affected services:
Vodacom South Africa Network

Dear Valued Clients,


Please be advised that Vodacom has scheduled emergency maintenance on one of their network nodes to resolve an APN routing issue - We anticipate a maximum downtime of 30 minutes during this maintenance window where SIM connectivity will be impacted.


We apologize for any inconvenience this may cause and appreciate your patience.


We will provide a further update once the maintenance has been completed.

May 11, 9:59 PM
Incident
Login Issues on CentralFlex Portals
Affected services:
CentralFlex ZA API
CentralFlex Global Platform
CentralFlex ZA Platform
CentralFlex Global API
Our team has applied a fix for the instability identified on a third-party dependency affecting CentralFlex Portal logins.

We are currently monitoring the environment closely to confirm full stabilisation.

If you are still experiencing issues, please contact our support team at support@ionlinesp.com and they will be happy to assist.
May 12, 7:55 PM
We have identified an active incident impacting CentralFlex Portals login. Customers may experience slow logins or intermittent failures when signing in.

Our investigation indicates the disruption is related to instability in an upstream third-party dependency used during our authentication flow. Our engineering team is monitoring the upstream service and implementing mitigations to restore normal login performance.

If you need urgent assistance while login is degraded, please contact our support team on support@ionlinesp.com and they will help action requests where possible.
May 12, 7:00 PM
Maintenance
Scheduled Maintenance for 10 May 2026
09 May 22:00 - 10 May 02:00 2026 UTC
Estimated duration: 4 hours
Affected services:
Vodacom South Africa Network

Dear valued client,


We would like to inform you of planned maintenance work that needs to be carried out on our core network in South Africa. During the change window, data traffic services may experience intermittent connectivity. The CentralFlex platform and APIs will remain available for this period of time.


Change Window Details:

Date: 10 May 2026

Start Time: 00:00 SAST

End Time: 4:00 SAST

Potential Downtime: 10 minutes

Affected Services: Data traffic


Should you experience any issues after the change has been completed, please don't hesitate to contact our support team at support@ionlinesp.com so we can escalate the issue for urgent resolution.


We thank you for your understanding and cooperation in this regard.


Sincerely,


iONLINE Team

May 09, 9:00 PM
Maintenance
Scheduled Maintenance for 3 May 2026
02 May 23:00 - 03 May 02:00 2026 UTC
Estimated duration: 3 hours
Affected services:
MTN South Africa Network
Vodacom South Africa Network

Dear valued client,


We would like to inform you of planned maintenance work that needs to be carried out on our core network in South Africa. During the change window, data traffic services may experience intermittent connectivity. The CentralFlex platform and APIs will remain available for this period of time.


Change Window Details:

Date: 3 May 2026

Start Time: 1:00 SAST | 23:00 UTC

End Time: 4:00 SAST | 2:00 UTC

Potential Downtime: 20 minutes

Affected Services: Data traffic


Should you experience any issues after the change has been completed, please don't hesitate to contact our support team at support@ionlinesp.com so we can escalate the issue for urgent resolution.


We thank you for your understanding and cooperation in this regard.


Sincerely,


iONLINE Team

May 02, 10:00 PM
March 2026
Maintenance
Scheduled Vodacom Maintenance - 19th to 20th March 2026
19 Mar 21:00 - 20 Mar 02:00 2026 UTC
Estimated duration: 5 hours
Affected services:
Vodacom South Africa Network

Dear Clients, Please note that Vodacom will be performing a scheduled maintenance, as per below :


Change Details


Field Name Value

Reference CRQ CHG0032881

Start date/Time 2026-03-19 23:00:00 SAST

Expected Completion time 2026-03-20 04:00:00 SAST

Reason for change CHG0032881| Migrate corporate APN to new Infrastructure

Customer Impact Customer Services will be impacted for 240min during the maintenance window


Kind regards,


Mar 19, 8:00 PM
Maintenance
Scheduled Vodacom Maintenance - 18th to 19th March 2026
18 Mar 21:00 - 19 Mar 02:00 2026 UTC
Estimated duration: 5 hours
Affected services:
Vodacom South Africa Network

Dear Clients, Please note that Vodacom will be performing a scheduled maintenance, as per below :


Change Details


Field Name Value

Reference CRQ CHG0032879

Start date/Time 2026-03-18 23:00:00 SAST

Expected Completion time 2026-03-19 04:00:00 SAST

Reason for change CHG0032879| Migrate corporate APN to new Infrastructure

Customer Impact Customer Services will be impacted for 240min during the maintenance window


Kind regards,


Mar 18, 8:00 PM
Maintenance
Scheduled Vodacom Maintenance - 17th to 18th March 2026
17 Mar 21:00 - 18 Mar 02:00 2026 UTC
Estimated duration: 5 hours
Affected services:
Vodacom South Africa Network

Dear Clients, Please note that Vodacom will be performing a scheduled maintenance, as per below :


Change Details


Field Name     Value

Reference CRQ            CHG0032879

Start date/Time            2026-03-17 23:00:00 SAST

Expected Completion time   2026-03-18 04:00:00 SAST

Reason for change     CHG0032879| Migrate corporate APN to new Infrastructure

Customer Impact        Customer Services will be impacted for 240min during the maintenance window


Kind regards,

Mar 17, 8:00 PM
Outage
CentralFlex UI down
Affected services:
CentralFlex ZA Platform
The team has implemented a fix and CentralFlex portal is now stable. If you experience any further issues please reach out to support@ionlinesp.com
Mar 19, 12:11 PM
CentralFlex Portal Stability
We’re pleased to confirm that the CentralFlex portal is now stable and fully operational. Our teams will continue monitoring to ensure ongoing reliability. Thank you for your patience.
Mar 17, 8:41 AM
We have identified an issue with our CentralFlex portal that is causing the user interface to become unresponsive. Please note that APIs and SIM connectivity remain fully operational and unaffected. We are actively working on a resolution and will restore full functionality as soon as possible.
Mar 17, 7:53 AM
Maintenance
Scheduled Vodacom Maintenance - 16th to 17th March 2025
16 Mar 21:00 - 17 Mar 02:00 2026 UTC
Estimated duration: 5 hours
Affected services:
Vodacom South Africa Network

Dear Clients, Please note that Vodacom will be performing a scheduled maintenance, as per below :


Reference CRQ CHG0032878

Start date/Time 2026-03-16 23:00:00 SAST

Expected Completion time 2026-03-17 04:00:00 SAST

Reason for change CHG0032878| Migrate corporate APN to new Infrastructure

Customer Impact Customer Services will be impacted for 240min during the maintenance window


Kind regards,

Mar 16, 8:00 PM
Maintenance
Vodacom Maintenance 11th March to 12th March 2026
11 Mar 21:00 - 12 Mar 02:00 2026 UTC
Estimated duration: 5 hours
Affected services:
Vodacom South Africa Network

Good day, clients.


We would hereby like to inform you of the planned maintenance work that needs to be implemented on the Vodacom network. Maintenance details are as follows:


Reference CRQ: CHG0032870


Start date/Time : 2026-03-11 23:00:00 SAST


Expected completion time: 2026-03-12 04:00:00 SAST


Reason for change: CHG0032870 | ASR9000 Software upgrade XR


Customer Impact: 40 min. Current IOS-XR requires additional features to be added.


We apologise for the inconvenience caused.


Kind regards,